Expansion scheme at Al Hassan Industrial Estate 70% complete
An expansion project at Al-Hassan Industrial Estate (HIE) is proceeding according to plan and that accomplishment reached 70 per cent, according to Jordan industrial Estates Company (JIEC) Director General Omar Juwaid.
He said during a tour of the facility Tuesday that despite a delay due to the coronavirus pandemic, the expansion scheme will be completed and ready to attract more investments early next year.
Juwaid told Petra in an interview that the project includes typical industrial buildings of about 18,000 square metres, roads, water, sewage, electricity and communications networks, lighting and other infrastructure services.
The project will boost capacity at the facility, which accounts for more than 80% of the Irbid governorate's industrial exports, in addition to the job opportunities the expansion will create, he said.
HIE Director Hani Thiabat said that the JD4 million expansion project, which kicked off in mid-2019, came after the operation of the first three phases of the industrial estate, which saw high investment demand in the various industrial fields.
The HIE, which was established in 1991, incorporates 134 facilities of the various industries at an investment volume of about JD448 million and a workforce of nearly 36,000.
An expansion project at Al-Hassan Industrial Estate (HIE) is proceeding according to plan and that accomplishment reached 70 per cent, according to Jordan industrial Estates Company (JIEC) Director General Omar Juwaid.
He said during a tour of the facility Tuesday that despite a delay due to the coronavirus pandemic, the expansion scheme will be completed and ready to attract more investments early next year.
Juwaid told Petra in an interview that the project includes typical industrial buildings of about 18,000 square metres, roads, water, sewage, electricity and communications networks, lighting and other infrastructure services.
The project will boost capacity at the facility, which accounts for more than 80% of the Irbid governorate's industrial exports, in addition to the job opportunities the expansion will create, he said.
HIE Director Hani Thiabat said that the JD4 million expansion project, which kicked off in mid-2019, came after the operation of the first three phases of the industrial estate, which saw high investment demand in the various industrial fields.
The HIE, which was established in 1991, incorporates 134 facilities of the various industries at an investment volume of about JD448 million and a workforce of nearly 36,000.
An expansion project at Al-Hassan Industrial Estate (HIE) is proceeding according to plan and that accomplishment reached 70 per cent, according to Jordan industrial Estates Company (JIEC) Director General Omar Juwaid.
He said during a tour of the facility Tuesday that despite a delay due to the coronavirus pandemic, the expansion scheme will be completed and ready to attract more investments early next year.
Juwaid told Petra in an interview that the project includes typical industrial buildings of about 18,000 square metres, roads, water, sewage, electricity and communications networks, lighting and other infrastructure services.
The project will boost capacity at the facility, which accounts for more than 80% of the Irbid governorate's industrial exports, in addition to the job opportunities the expansion will create, he said.
HIE Director Hani Thiabat said that the JD4 million expansion project, which kicked off in mid-2019, came after the operation of the first three phases of the industrial estate, which saw high investment demand in the various industrial fields.
The HIE, which was established in 1991, incorporates 134 facilities of the various industries at an investment volume of about JD448 million and a workforce of nearly 36,000.